ALERT: Learn more about major Portage Bay construction efforts

View the weekly vibratory casing installation schedule (Last updated July 20, 2026)

Vibratory casing installation in Portage Bay schedule: Week of July 20-26

Date: May 2026 to mid-summer 2026 (at least)

Time: Between 7 a.m. and 10 p.m. on weekdays and 9 a.m. to 10 p.m. on weekends

Activity details:

High-impact construction

Impact type:

DaytimeNoiseVibration

Crews are now using vibratory hammers to install large diameter steel casings in Portage Bay. This work is helping build the new foundations for the future westbound Portage Bay Bridge.

Crews started this work on the northwest side of the temporary work trestle near Boyer Avenue East and will work back and forth between casings, moving east toward Montlake Boulevard.

Below is an update on the planned schedule of vibratory casing installation in Portage Bay. This schedule will be updated weekly and is meant to provide a general overview of planned work. Please note construction schedules can – and often do – change so please check this link regularly for potential updates.


Installation schedule for the week of July 20-26

  • Tuesday, July 21, between 7 a.m. up to as late as 10 p.m.
  • Wednesday, July 22, between 7 a.m. up to as late as 10 p.m.
  • Friday, July 24, between 7 a.m. up to as late as 10 p.m.
  • Saturday, July 25, between 9 a.m. up to as late as 10 p.m.

Map of current progress drilled shaft installation

Graphic shows the current installation progress as of July 20, 2026.


Nearby neighbors will experience noise and vibration during daytime construction through mid-summer. After crews finish installing the casings, they will begin work on the drilled shafts.

Typical work hours: 7 a.m. to 10 p.m. weekdays and 9 a.m. to 10 p.m. on weekends

Contact Info

Email:  sr520bridge@wsdot.wa.gov 24-hour construction hotline: 206-319-4520