Single lane closures on Delmar Drive East May 28 - June 7
Date: May 28, 2024 to June 7, 2024
Time: Weekdays from 9:30 a.m. to 3:30 p.m.
Activity details:
-
Street and lane closure
Impact type:
-
Bike/pedestrian
-
Noise
Description: In preparation for the Portage Bay Bridge and Roanoke Lid Project, crews will drill approximately three test holes (also referred to as "geotechnical test borings") on Delmar Drive East near East Interlaken Boulevard to collect soil samples. Work begins Tuesday, May 28, and will continue through Friday, June 7.
Traffic: Single lane closures on Delmar Drive East between 11th Avenue East and East Interlaken Boulevard from 9:30 a.m. to 3:30 p.m., Monday through Friday. Flaggers will be on site directing traffic.

Contact Info
Email: sr520bridge@wsdot.wa.gov
24-hour construction hotline:
206-316-2559
Note: This tool is presented for planning purposes only. Construction is inherently dependent on weather and other factors, and activities are subject to change.